Advertisement

Underwater bridge base building is on schedule

Reading Time:1 minute
Why you can trust SCMP
0

SITE preparation and foundation works are on schedule for the Tsing Ma suspension bridge.

Subcontractors in the Anglo-Japanese joint venture are placing base concrete in the Tsing Yi tower footings and piers on the Tsing Yi island side of the project.

Major excavation for the anchorages and foundations of the two towers has been completed.

On the Ma Wan side, a portion of the batch plant has been commissioned, and form work has started on the first land-side pier between the anchorage and the tower.

The Ma Wan Tower requires underwater site preparation, unlike the Tsing Yi tower. Special concrete caissons were built on a submersible barge, and the barge was sunk until the caissons floated off. The caissons, which are floating in the water nearby, arehollow. When the site for the caissons is complete, they will be sunk and pumped with concrete to within seven metres of the top. This space will take the tower legs.

Joint venture partners Mitsui-Costain are conducting form work operations, including the bending of reinforcing steel.

Advertisement