NOTABLE OFFENDERS

PUBLISHED : Thursday, 11 January, 2007, 12:00am
UPDATED : Thursday, 11 January, 2007, 12:00am

Datang International Power Generation


Failed to shut down generators at the Tangshan Power Plant as required


China Huadian Corporation


Failed to shut down a generator at the Panzhihua Power Plant as required


China Huaneng Group


Failed to shut down generators and install desulfurisation devices at its Wulashan Power Plant


China Guodian Corporation


Failed to install desulfurisation devices at its Puyang Heat and Power Plant


Luliang Coking Plant


Failed to install waste treatment facilities as required


Yemazhai Power Plant


Expanded operation without Sepa approval


Laiwu Iron and Steel Group


Expanded operation without Sepa approval


Jinan Railway Administration


Building railway without doing environmental assessments


Haixin Iron and Steel


Conducting renovation work without environmental assessments


Baogang Group Co Ltd


Started projects without conducting environmental assessments.