Advertisement

Opinion | Did MTR fail shareholders by not disclosing rail project delay sooner?

Albert Cheng says the findings of an internal investigation show several points when the company could have made public the problems

Reading Time:3 minutes
Why you can trust SCMP
0
The committee's report was unveiled last week. Photo: Edward Wong

The findings of an internal investigation into the two-year delay of the MTR Corporation's express rail link project, released last week, have been widely dismissed as a whitewash in the media.

The 93-page report - by a committee set up by the company's board - concluded that the handling of the project delay had led to a serious loss of credibility for the company. However, it does not recommend taking any action against any of its officers responsible for overseeing the construction work.

If one reads the report's chronology of events carefully, there would seem to be a strong case for the Securities and Futures Commission to look into whether the MTR board failed to comply with the statutory requirements to disclose price-sensitive, or inside, information in an appropriate and timely manner.

In this case, the MTR's failure to do so appears to have compromised shareholder interests.

According to the report, the first sign of trouble surfaced at a meeting as early as April last year, when the principal contractor for the West Kowloon terminal told the MTR's project team for the Hong Kong section of the Guangzhou-Shenzhen-Hong Kong express rail link that the 2015 timetable could not be met.

The Apple Daily carried an exclusive story on the problem in May last year. The MTR responded with a flat denial.

Advertisement