Hong Kong playing catch up on best practises in project management

While Hong Kong has delivered some outstanding infrastructure projects over the years, local best practise must evolve to deal with the ever-increasing cost of construction projects

While Hong Kong has delivered some outstanding infrastructure projects over the years, local best practise must evolve to deal with the ever-increasing cost of construction projects

As outlined in the 2016/2017 Budget, the Hong Kong government plans to spend more on infrastructure projects than on health, education, or social welfare. With infrastructure spending targeted at HK$85.6 billion (17.6 per cent of total government expenditure) and with this level of expenditure planned to continue for several years, the government must demonstrate that this money is being effectively and efficiently spent.

With these capital works projects, the launch of the government’s new Project Cost Management Office (PCMO), has been welcomed by many. Hong Kong has a strong history of delivering outstanding development projects. However in recent years local best practise has stagnated and Hong Kong is falling behind global industry standards. The crucial test for the PCMO is whether it will deliver significant savings and efficiencies in the coming years.

Value for money is a justified overriding principle of public sector procurement. However, the acceptance of the lowest tender often leads to future problems. To use a simple analogy, if you were to have open-heart surgery, would you want to choose the surgeon who offered the lowest price to do the job, or the one who was most experienced and offered the best chance of survival?

The lowest bid does not necessarily offer best value for money. If the contractor has essentially “bought” the job at below its true cost, there will be a focus on recovering costs either through claims to the employer, or by denying payments due to sub-contractors.

If the contractor has essentially ‘bought’ the job at below its true cost, there will be a focus on recovering costs either through claims to the employer, or by denying payments due to sub-contractors

In comparison, organisations such as MTRC have adopted more innovative tender processes to take greater account of the risk profile of the contractor’s bid and this results in selecting the contractor that offers greater certainty of delivery, which is not necessarily the cheapest tender price. This same approach should be investigated by the PCMO.

Recently the government has been using a method called Reference Class Forecasting to compare and estimate major project costs against global benchmarking databases of similar projects completed elsewhere. Whilst this is a welcome development, Hong Kong construction projects still typically rely on a single overall cost estimate. As such, these estimates do not adequately reflect the inherent uncertainty in estimating budgets for projects spanning many years.

A more effective approach, given the range of possible risks and costs in Hong Kong, would be to implement more sophisticated methods using cost probabilities and techniques (such as Monte Carlo simulation) which give a more realistic idea of all possible cost outcomes and a probability for each of those outcomes.

The government has also indicated its desire to implement the New Engineering Contract (NEC) on all major upcoming projects. NEC is widely adopted across jurisdictions including the UK, South Africa, Australia and New Zealand, and is now being slowly introduced in Hong Kong in place of the traditional General Conditions of Contract (GCC). The NEC contract promotes a more collaborative approach to projects, as seen in the frequently quoted clause 10.1 “The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation.”

Use of the NEC target cost contract, one of the NEC options, will provide greater emphasis in the control of costs with closer alignment of the contractor’s and employer’s interests (the “painshare/gainshare”). It is hoped that this will not only reduce costs, but also deliver faster, better projects.

Workers seen at the Hong Kong-Zhuhai-Macau Bridge construction site in 2014. Photo: K.Y. Cheng
Workers seen at the Hong Kong-Zhuhai-Macau Bridge construction site in 2014. Photo: K.Y. Cheng
Whilst the NEC provides a refreshing approach compared to the usual adversarial contract conditions such as those embodied in the GCC, it requires prompt decision making and quick turnaround of communications to ensure that issues and changes of scope are dealt with as they occur and are not deferred to a legal brawl at the end of the contract. For this approach to work the Government Works Departments must ensure they have adequate staffing with agile and responsive project teams, as well as adopting accelerated and decentralised decision-making.

Techniques such as BIM (Building Information Modelling) should also be encouraged and utilised early in the project life cycle, which will help in identifying design issues and inefficiencies, thereby further avoiding unnecessary cost.

Where issues do arise, the early identification and resolution of these matters can provide a critical contribution to the control of the final costs of the project.

While Hong Kong has delivered some outstanding infrastructure projects over the years, local best practise must evolve to deal with the ever-increasing cost of construction projects. The PCMO can play a key part in controlling this major part of Hong Kong’s annual budget. The project management methods we have outlined are a logical step for the PCMO to consider to once again match global best practise.

Steve Root is a director of construction consultancy Contracts Group