Cheung Ching tunnels triumph for Dragages
Dragages has already moved on site in preparation for work on the Cheung Ching tunnels.
THE Route 3 contract for the construction of the Cheung Ching tunnels has been awarded to Dragages et Travaux Publics, the local Hongkong arm of the French construction giant Bouygues.
Speaking about the award of the $856-million contract, Dragages managing director Mr Michel Betant said the nearest other bidder was 15 per cent higher.
The award of the contract for what must be the biggest tunnel project underway in Asia, took place on March 5, and Dragages gained possession of the site within 30 minutes.
The award is a triumph for Mr Betant, and follows a series of near misses with other Airport Core Projects for the Hongkong branch of the French contracting firm.
Mr Betant and his team spent millions of dollars and thousands of man hours competing for the Tsing Ma Bridge and the Kap Shui Mun bridge projects, only to be beaten into second place.