Indecision on paying for public facilities hangs over MTRC project
A dispute over the costs of building public facilities is threatening to delay a massive housing development at the Mass Transit Railway Corp's (MTRC) future depot site in Tseung Kwan O.
The MTRC is fighting to gain government concessions to free it from the costs of associated government, institution and community (GIC) facilities in the property project.
However, the Government is yet to decide on the matter, placing doubt over whether the 32.4 hectares earmarked for the depot site and related property development will be approved for development on schedule next month.
Deputy Director of Lands John Corrigall said the GIC building costs remained an issue to be resolved and the Lands Department might fail to grant the site as scheduled.
The disagreement involves millions of dollars as the Tseung Kwan O project comprises a large amount of GIC facilities.
The MTRC considers it reasonable for the Government to share the costs of building such facilities in the project, which include seven schools, community facilities and two public transport interchanges.