Advertisement
MORE than 150 metres has been excavated on the Cheung Ching tunnels' project, engineers from the French-owned Dragages company said.
Advertisement
Work on the ''pilot galleries'' is expected to begin this week.
These will form the main working area as the twin three-lane tunnels are bored through 1.5 km of Tsing Yi island's solid granite.
Work is progressing about four metres a day from both east and west. The breakthrough is expected in March 1995.
The finished tunnel is expected to be handed over to the Highways Department in November 1996.
Advertisement
At its peak, the Cheung Ching tunnel project is expected to employ 200 people. The tunnel's project manager is Jean-Pierre Barral.
Advertisement