Advertisement

Project racing ahead of plan

Reading Time:3 minutes
Why you can trust SCMP

JUST 46 weeks into the 31/2-year Site Preparation Contract, the Chek Lap Kok airport project is racing ahead, easily exceeding construction targets.

Advertisement

More than 270 hectares of new land has been added to the site in a construction process that moves about 800,000 tonnes of material each day.

A total of 938 hectares of land will, eventually, be reclaimed.

Speaking at an Airport Projects seminar organised by the Hong Kong Institution of Engineers and the Provisional Airport Authority, PAA project director Doug Oakervee said 34.6 per cent of the necessary excavation had been completed and the work was aheadof schedule.

The airport island of Chek Lap Kok employed 1,700 people, he said.

Advertisement

By mid-1996 - when the Site Preparation Contract is completed - more than 310 hectares of land will have been excavated at Chek Lap Kok and Lantau island.

Advertisement