Advertisement

Keeping Queen's Pier in its place impractical: engineers

2-MIN READ2-MIN

On-site preservation of Queen's Pier has been called 'infeasible' because of the difficulty in changing the location of a planned MTR tunnel, according to the Institution of Engineers.

The group believes the most practical way to preserve the pier would be to dismantle it and rebuild it later - either elsewhere or on the original site after tunnel construction.

'We consider it technically infeasible to change the alignment of the planned airport railway extended-overrun tunnel,' institution spokesman Wong Chi-ming said.

Advertisement

'Shifting it to avoid the pier would involve gazetting and statutory procedures that would incur huge prolongation costs under the Central Reclamation III contract,' Mr Wong said.

Underpinning the pier for building the tunnel would involve big technical difficulties and safety hazards, he added.

Advertisement

'This is an extremely risky option,' he said. 'The substantial width of the tunnel - more than 40 metres - also makes it highly infeasible.'

The group estimated such an option would take 31/2 years to carry out and incur extra costs of HK$865 million - HK$565 million in additional work and HK$300 million in delay costs.

Advertisement
Select Voice
Select Speed
1.00x