New World Development will pull down and rebuild the existing floors of Towers 1 and 8 at its Pavilia Farm III project near Tai Wai station. Photo: May Tse New World Development will pull down and rebuild the existing floors of Towers 1 and 8 at its Pavilia Farm III project near Tai Wai station. Photo: May Tse
New World Development will pull down and rebuild the existing floors of Towers 1 and 8 at its Pavilia Farm III project near Tai Wai station. Photo: May Tse

New World carried on selling flats at The Pavilia Farm III after concrete defects were found, as engineers didn’t deem them serious

  • The developer enjoyed two lively sales weekends after the defects were found in two blocks later earmarked for demolition
  • Some buyers struck a forgiving tone, saying New World had acted properly and would learn from the experience

Topic |   New World Development
New World Development will pull down and rebuild the existing floors of Towers 1 and 8 at its Pavilia Farm III project near Tai Wai station. Photo: May Tse New World Development will pull down and rebuild the existing floors of Towers 1 and 8 at its Pavilia Farm III project near Tai Wai station. Photo: May Tse
New World Development will pull down and rebuild the existing floors of Towers 1 and 8 at its Pavilia Farm III project near Tai Wai station. Photo: May Tse