Hong Kong railway operator MTR posts 37.5 per cent decline in net profit for half year
In a briefing to reporters MTR chief executive Lincoln Leong Kwok-kuen said that “given the very tight timetable, there remains a number of risks” that could mean the end-December target completion date is not met on the HK$16.9 billion South Island line (East) linking Admiralty to Wong Chuk Hang. He added that costs in excess of the budgeted HK$16.9 billion are “not expected to be material”.
Outstanding jobs to be completed include civil, electrical and mechanical work, as well as inspection by the government.
In addition, citing “external events” including archaeological finds, late handover of critical work sites by other parties and additional underground works, Leong said the 17-km Shatin-to-Central Link is “likely” to see its cost estimate “revised upwards significantly”.
He declined to give any cost revision estimate, saying a cost review will only be completed in the second half of next year since the north-south segment of the project is only 35 per cent complete.
MTR had previously said an 11-month delay and unforeseen work arising from the archaeological finds would cost an additional HK$4.1 billion.