Lee Chack-fan was revealed to be an independent non-executive director of Paul Y Engineering, a key contractor on the rail link's underground terminus in West Kowloon, where excavation difficulties have been pinpointed by the MTR as being at the centre of the delay.

Rail link farce as head of inquiry into MTR high-speed train delay quits

Professor given task of leading independent investigation into controversy is found to be on the board of one of the project's key contractors

Topic |   Hong Kong MTR

TOP PICKS

Lee Chack-fan was revealed to be an independent non-executive director of Paul Y Engineering, a key contractor on the rail link's underground terminus in West Kowloon, where excavation difficulties have been pinpointed by the MTR as being at the centre of the delay.
READ FULL ARTICLE