-
Advertisement
MTR Corporation
Hong Kong

Hong Kong's HK$71.5b express rail debacle down to poor supervision and execution: experts

Poor supervision and execution led to delays and higher costs on HK$71.5b project: expert panel

Reading Time:3 minutes
Why you can trust SCMP
Passengers were left in the dark due, in part, to the MTR's culture of 'discouraging elevation of bad news', an expert panel found. Photo: Sam Tsang
Amy Nip

The Highways Department and railway powerhouse the MTR Corporation have respectively failed in their roles to supervise and execute a HK$71.5 billion high-speed link to Guangzhou that is now plagued by delays and a budget overrun, an independent expert panel says.

Completion of the Hong Kong section of the Guangzhou-Shenzhen-Hong Kong Express Rail Link has been pushed back by two years to 2017, and its budget has snowballed to about HK$71.5 billion from HK$65 billion.

And the MTR Corp's corporate culture of "discouraging elevation of bad news without solutions" was partly to blame, the three-member panel said.

Advertisement

Also at fault was the MTR project team's "over-optimism" about the completion date and overreliance on measures it believed, without verifying their effectiveness, would minimise delays, according to the panel's 187-page report, unveiled yesterday.

On the part of the department, it failed to supervise the project's progress and lacked a master mechanism to define overall delivery strategies, roles and obligations between the MTR, the government - its controlling shareholder - and other parties involved, the report said.

Advertisement

In July 2013, the department's consultant, Jacobs China, estimated a potential delay of almost 11 months to July 2016, but the department did not ask the MTR to review in depth the works progress, the report noted.

Advertisement
Select Voice
Choose your listening speed
Get through articles 2x faster
1.25x
250 WPM
Slow
Average
Fast
1.25x