A sudden fire that destroyed a HK$3.8 million prototype electric bus last year was caused by “operational errors” by mainland technical staff, who compromised testing procedures, an investigation has confirmed.

The locally designed bus, the city’s first, was part of a HK$40 million project funded by the government’s Innovation and Technology Fund for the Hong Kong Productivity Council to develop electric vehicle technologies.

The council partnered with Green Dynamic Electric Vehicle, a subsidiary of Hong Kong-listed China Dynamics (Holdings), which splashed out HK$20 million for the project and was granted the intellectual property rights to the technologies.

Advertisement

The council’s incident report stated that several Green Dynamic technical support staff members who conducted tests on the bus in Dongguan last October had kept the council in the dark about some performance test results.

“Some of the technical support staff ... compromised the water sealing of the battery casings during performance tuning and inspection. Subsequent seepage of water into the compromised battery casings eventually led to short-circuiting,” the report said.

Advertisement

The bus was reduced to a charred wreck after it went up in flames at a parking site in Yuen Long last December, just after it had passed a road test and was ready for commercialisation.

While it was designed for Hong Kong’s winding roads, the vehicle was made on the mainland due to a lack of manpower and space to build it in the city.