Keep it moving: faster and less costly completion of Hong Kong lifts and ramps urged
Report finds retrofitting completed for only 60 of 184 footbridges, elevated walkways and subways

The Audit Commission has told the government to speed up the retrofitting of lifts and ramps for footbridges, elevated walkways, and subways as well as curtail cost overruns, after it was revealed that two-thirds of such works were not completed, with some having deadlines for as early as next year.
The former Transport Bureau began retrofitting works for footbridges, elevated walkways and subways in 2001.
But an audit report released on Wednesday showed that, as of December last year, retrofitting works had been completed for only 60 out of 184 footbridges, elevated walkways and subways that were found to be feasible for such works. Thirteen works had not even commenced.