Extended Hong Kong bridge seawall works just temporary, officials insist
Authorities also confident HK$36 billion boundary-crossing facility built on artificial island to be finished on schedule

Authorities were also optimistic the Hong Kong section of the multi-billion-dollar project, including a HK$36 billion boundary-crossing facility built on an artificial island, would be completed on schedule, despite a lawmaker’s concern about the island’s stability.
While the department confirmed such movements, it insisted the matter had been taken care of and denied there was any cover-up.
On Thursday, project manager Albert Lee Wai-bun led 20 lawmakers and the media in a three-hour site visit.

He explained the additional reclamation was in fact a “temporary rockfill platform” to strengthen the seawall. After the seawall’s movements in 2014, the platform was enlarged.